Merlin Properties
Duration
6 months - 3 phases
Location
Madrid

In Arturo Soria Plaza shopping centre the total production and ventilation was replaced.

Thanks to an exhaustive planning, it was possible to carry out the works without stopping the centre and without interfering in the activities of the clients or the operators.

Three new refrigeration units were installed and both the primary and secondary collectors were modified. In addition, new air-conditioning units and new boilers were installed.